Maison Blanc
Project Details
Client: Next Construction
Location: Bondi NSW
Project: Residential, 16 Apartments
Completion date: 2015
Our team completed a package consisting of all aspects of carpentry in these high end apartments. A timber frame penthouse floor and roof along with stairs, skirting, door frames, doors and hardware highlighted our teams all round carpentry skills.
Works Complete
Construct timber frame penthouse
Install timber stairs
Install timber door frames, Doors and door hardware
Install timber skirting
Install bathroom p.c items